Azura Edo Gas Plant

*P&ID had no guarantee, yet Nigeria was liable
*Presidential Adviser lists consequences if Buhari administration had cancelled agreement in 2015
*Nowhere in all agreements is Nigeria liable to pay $1.2b

The Presidency has cleared the air on the controversy about the Azura-Edo Independent Power Project (IPP), detailing the timeline of events and why the Partial Risk Guarantee (PRG) is not an issue.

Engr Ahmed Rufa’i Zakari, Special Adviser to the President on Infrastructure explained that Azura-Edo is an asset to Nigeria as it contributes eight per cent of power to the national grid.

“Over the past week, there has been an unnecessary controversy about the Azura-Edo Independent Power Project (IPP) especially the concerns about who signed the transaction documents and who did not sign, thus ignoring the consequences of backing out of the agreements by the Federal Government.

Advertisement

“The Azura-Edo IPP is a functional 461MW power plant. It is owned by a group of investors led by an internationally reputed firm – Actis and includes the Edo State government as part of the investment consortium. Today, the plant supplies over 8% of the power on Nigeria’s National Grid. Clearly, the controversy as to who signed the agreements has no real basis, if indeed the only quest is for the plain truth.

“Since the Buhari government had chosen not to repudiate the deal, it went ahead to issue the required legal opinion and signed the World Bank guarantees that had been initiated in April 2014. In fact the main Power Purchase Agreement was signed in 2013.

Zakari then quizzed, “If at the point the Buhari government came into office, it repudiated the contracts, what would have happened?

“First, because there was already a valid and binding contract between the Federal Government and Azura-Edo, that would have led to an international case similar to the P&ID scenario.

Advertisement

“In the P & ID case, the Federal Government was sued for breaching the terms of a contract to build a gas processing plant. Despite the fact that no part of the plant was ever built and no government or World Bank guarantees were given, the Arbitral Tribunal found Nigeria liable in the sum of $9.6 billion. So, clearly, guarantee is not the issue at stake here.

“The second consequence is that we would simply not have, today in the country, a 461 MW power plant in Nigeria, with a significant contribution to our national grid.

“Third, it would definitely have affected our credit rating and credibility as an investment destination. Some of the most reputable international banks and investors that were involved in the project include Development Finance Institutions of the US, UK, France, Germany, the Netherlands and Sweden.

He went on to add that, “Again, laying out the facts already stated in previous communication about this matter, there is no doubt at all that the binding agreements which brought about the plant were signed in 2013 and 2014. On April 22, 2013, the Power Purchase Agreement was signed.

“This is the contract that contained the Take or Pay clause, which is now the crux of the manufactured controversy. That clause is however standard in PPAs. What it says is that government will pay for the energy produced by the plant, whether it uses it or not.

Advertisement

“Without that assurance, nobody would invest money in such a huge power plant. Large infrastructure projects are executed using project finance principles and debt, guarantees of repayment are always needed to reach financial close.

“On October 22, 2014, the second agreement was signed. That is the Put Call Option Agreement (PCOA), which establishes the formula for determining the amount payable by government, if it has to take over the Plant. The PCOA for power plants is actually a novel approach pioneered in Nigeria. It ensures that unlike other contracts where a contract default would trigger penalties alone, in the case of Azura a default would allow Nigeria to purchase the asset. This ensures that the country has a contingent asset alongside a contingent liability. The PCOA approach has now become standard in West Africa and is being adopted across the developing world.

“Apart from these signed contracts, Nigeria as host country, also made a commitment to back up the transaction. The Ministry of Finance issued a letter of support to the World Bank Multilateral Investment Guarantee Agency (MIGA) in April, 2014.

“Those who argue that the signing of the World Bank Guarantees makes the Federal Government under Buhari responsible for contracting Azura need only to look at the two basic transaction documents.

Advertisement

“Another curious mischief in this controversy is the assertion that Nigeria will become liable in the sum of $1.2billion if it defaults on the Azura contract. Nowhere in any of the documents signed from 2013 to 2015 is any such figure mentioned.

“The only possible payout indicated in any of the agreements is in case the put and call option is activated. In that event, the cost of the plant would be worked out using a formula and become due for payment, but at least Nigeria will get in return a functional 461MW plant.

“We have challenges in our power sector that the Government is actively working to mitigate, making the Azura contract a scape goat is not the answer.”

Advertisement
Advertisement
Click to comment

Leave a Reply

Your email address will not be published. Required fields are marked *

Copyright © 2015 - 2024 ChronicleNG

Discover more from Chronicle.ng

Subscribe now to keep reading and get access to the full archive.

Continue reading