Close Menu
Chronicle.ng
    Trending Stories
    SERAP urges Tinubu to probe alleged obstruction of NDDC audit report

    SERAP urges Tinubu to probe alleged obstruction of NDDC audit report

    July 6, 2025
    MURIC demands sharia courts, public holidays in Southwest on Fridays

    MURIC demands sharia courts, public holidays in Southwest on Fridays

    July 6, 2025
    NIPOST rolls out cashless operations nationwide from July 1

    NIPOST denies drug peddling

    July 6, 2025
    Facebook X (Twitter) Instagram
    Trending
    • SERAP urges Tinubu to probe alleged obstruction of NDDC audit report
    • MURIC demands sharia courts, public holidays in Southwest on Fridays
    • NIPOST denies drug peddling
    • NLC threatens mass protest over rising poverty, insecurity
    • Death toll in Texas flood disaster hits 51 including 15 children
    • Arsenal sign Martin Zubimendi for £60m from Real Sociedad
    • Cross River women to protest naked over cocoa estate privatisation
    • Adelabu meets Oyo stakeholders, declares 2027 governorship ambition
    Facebook X (Twitter) Instagram
    Chronicle.ngChronicle.ng
    Subscribe
    Sunday, July 6
    • News
      • Nigeria News
      • World News
      • Headlines News
    • Politics
    • Business
    • Sport
    • Entertainment
    • Contact Us
    Chronicle.ng

    FG extends Lagos-Ibadan railway project completion deadline

    Chronicle EditorBy Chronicle EditorNovember 25, 2019No Comments2 Mins Read
    Facebook Twitter Telegram WhatsApp
    railway Lagos-Ibadan
    Facebook Twitter WhatsApp

    The Federal Government has extended the completion date of the Lagos-Ibadan railway project to April 2020.

    The project was initially scheduled to be completed by February 2020, but Minister of Transportation, Rotimi Amaechi, during an inspection tour of the project at the weekend, said that the contractor, China Civil Engineering Construction Company (CCECC), had pleaded for an additional two months for the completion of station buildings and communication signals.

    Amaechi said: “We are no longer giving ourselves the time, the contractor is the one giving us the time.

    “The initial contract was from Ebute-Metta but because we wanted it to end at the seaports, we extended it and that is where the challenges are.

    “The fact is that they can get to Ebute-Metta soon but getting there without getting to Apapa will not achieve much because we need to clear the gridlock and the easiest way to do it is to get the track to seaport, that way, cargoes will be loaded to wagons and taken to Ibadan.”

    READ ALSO: Police Arrest Rogue Officers, Recover Extorted N705,000

    The minister, who further blamed the delay in the project on dealing with urban renewal, building new flyovers, overhead bridges, underpasses, pipes, sewage, stealing of their equipment, said that they did not initially get the needed support as some people are still in court over the lands taken from them.

    Explaining reason for the delay on the part of the contractors, he said initially, they were planning to import some materials, such as glasses and doors, from China but the railway project contractor has agreed to source the materials from Nigeria so that it can meet up with the deadline.

    He said: “Before, they wanted to import glasses and doors. The pressure we are putting is now making them to buy the glasses and doors in Nigeria to quicken the process.”

    On the commencement of the free train service on November 30, Amaechi said: “Although there are not enough coaches and locomotives but we will start with as many as we can take pending when the 20 locomotives that we imported will arrive as it is expected that the coaches would have arrived and cleared latest by second week in January 2020.”

    Source

    Share. Facebook Twitter Telegram WhatsApp

    Keep Reading

    SERAP urges Tinubu to probe alleged obstruction of NDDC audit report

    SERAP urges Tinubu to probe alleged obstruction of NDDC audit report

    MURIC demands sharia courts, public holidays in Southwest on Fridays

    MURIC demands sharia courts, public holidays in Southwest on Fridays

    NIPOST rolls out cashless operations nationwide from July 1

    NIPOST denies drug peddling

    NLC threatens to shut down Abuja after July 3 over unpaid wages

    NLC threatens mass protest over rising poverty, insecurity

    Benue women protest youths arrest by police over killing of Kano travellers

    Cross River women to protest naked over cocoa estate privatisation

    Adelabu meets Oyo stakeholders, declares 2027 governorship ambition

    Adelabu meets Oyo stakeholders, declares 2027 governorship ambition

    Add A Comment
    Leave A Reply Cancel Reply

    Subscribe to News

    Be the first to get the latest news updates from ChronicleNG about world, sports, politics etc

    SERAP urges Tinubu to probe alleged obstruction of NDDC audit report

    SERAP urges Tinubu to probe alleged obstruction of NDDC audit report

    July 6, 2025
    MURIC demands sharia courts, public holidays in Southwest on Fridays

    MURIC demands sharia courts, public holidays in Southwest on Fridays

    July 6, 2025
    NIPOST rolls out cashless operations nationwide from July 1

    NIPOST denies drug peddling

    July 6, 2025
    NLC threatens to shut down Abuja after July 3 over unpaid wages

    NLC threatens mass protest over rising poverty, insecurity

    July 6, 2025
    Floods, landslides kills 19 dead in Bosnia

    Death toll in Texas flood disaster hits 51 including 15 children

    July 6, 2025
    Facebook X (Twitter) Instagram
    • Politics
    • News
    • Sports
    • Business
    • About Us
    © 2025 ChronicleNG

    Type above and press Enter to search. Press Esc to cancel.