Julius Berger abandons Lagos-Ibadan Expressway

Published

on

Four killed in crash Involving 21 persons on Lagos-Ibadan Expressway


The Federal Ministry of Power, Works and Housing has announced that Julius Berger Nigeria Plc has finally suspended work on the Lagos-Ibadan Expressway.

It sad the development was not unconnected with delays in the payment of agreed contract fees for work already done.

Checks have shown that the contractor handling the reconstruction and expansion works on the Section II from the Sagamu interchange to Ibadan, Reynolds Construction Company Nigeria Limited, with Contract No. 6205, had suspended further work on the project due to an outstanding debt of N8.94bn.

The RCC had in a letter addressed to the Minister of Power, Works and Housing, Babatunde Fashola, and dated June 2, 2017, called his attention to the worsening financial situation of the project and pleaded for his intervention in order to ensure the continuation of work on the site.

Read Also Niger Delta militants vow to resume attacks September 1

Advertisement

The Julius Berger letter stated, “It has become evident that the required adequate funding for the continuation of the project is not available. We trust that you will understand that, therefore, and as a consequence of the unacceptable financial risk to Julius Berger Nigeria Plc, we are left with no choice than to immediately commence suspension of the works on the project, as earlier notified.”

However, Fashola, in a statement issued by his Special Adviser on Communications, Mr. Hakeem Bello, on Sunday, stated that the two contractors working on sections of the Lagos-Ibadan Expressway, Messrs Julius Berger and RCC had given notice of suspension of work on the site.

According to Fashola, the letter from the Managing Director, RCC, Mr. M. Nakhla, which was dated June 2, 2017, stated, “In view of the irregular payment and the attendant cash flow problem, we shall be constrained to suspend further execution of work unless there is an appreciable improvement in the project’s cash flow and adequate funding arrangement is put in place for further works.”

Fashola said the letter was co-signed by the Division Manager, Julius Berger, Mr. W. Loesser; and the Commercial Division Manager, Mr. T. Meletschus.